彩钢瓦墙面该怎么安装才正确?

来源:http://www.jnqkgjg.com 日期:2019-03-04 发布人:admin

彩钢瓦墙面设备方法:

Color steel tile wall equipment method:
1、彩钢瓦设备是在高空,作业人员应做好   维护措施,墙面压型板类型标准为V3016,板厚为0.8MM,且一次设备长度为15m以上,针对墙面施工长度较长,选用单片人工拉起的办法。
1. The color steel tile equipment is at high altitude. Operators should take good maintenance measures. The type standard of the wall profiled plate is V3016, the thickness of the plate is 0.8MM, and the length of the primary equipment is more than 15 meters. In view of the long construction length of the wall, a single manual pull-up method is selected.
用固定卡头卡在天沟上口的檩条上,然后用螺丝紧固,再把滑轮挂在吊鼻上,用16的麻绳作拉绳,人工拉起。在每块彩板上端中心部打孔,孔到顶端间隔8CM,并用6钢筋弯成小于45度挂钩挂住上移。为了   拉起时再用¢16麻绳从瓦长的1/3处捆扎作为稳住线用人控制,以防起风时飘摆形成伤瓦和伤人。
Fixed clamp head is clamped on purlin at the top of Tiangou, then fastened with screw, then pulley is hung on suspension nose, and 16 hemp rope is used as pulling rope, which is pulled up manually. Perforate holes in the center of the top of each color board, with an interval of 8CM between the holes and the top, and bend 6 steel bars into hooks less than 45 degrees to move upward. In order to use 16 hemp rope to tie from one third of the tile length as a stabilizing line for human control, so as to prevent tiles and injuries from floating in the wind.
2、另外在彩钢瓦长的3/4处边部打孔增加辅佐拉线,上面作业人员系好   带用力提高与主拉线同步上拉,然后减轻了主线承重,克服了周围面上瓦出现的折断表象又确保了   。
2. Additionally, the auxiliary pull-up line is added at the edge of 3/4 of the length of the color steel tile. The upper operator fastens the belt to improve the pull-up synchronously with the main pull-up line, and then reduces the load-bearing capacity of the main line, which overcomes the broken appearance of the tile on the surrounding surface and ensures it.
3、待彩钢瓦拉到方位后,先用电自攻丝从底部暂时固定待瓦入位后松钩微调,终固定,固定结束去掉周围面的维护绳。
3. When the color steel tile is pulled to the azimuth, it is temporarily fixed from the bottom by self-tapping, and then slightly adjusted by loosening the hook. Finally, the maintenance rope around the tile is removed at the end of fixing.
4、在墙皮外边倒挂扒梯(用¢16圆钢做成),上端挂在天沟上底部两支点着地,操作作业把   带系在梯撑上。在龙门梯内每道作业向前滑动龙门梯进行,这么即确保操作的   性又确保固定彩板的灵活性。
4. Hang the ladder upside down outside the wall skin (made of 16 round steel). The upper end hangs on the two fulcrums at the top and bottom of the trench, and tie the belt to the ladder brace during the operation. In the gantry ladder, each operation is carried out by sliding the gantry ladder forward, which ensures the operability and the flexibility of the fixed color plate.
5、彩钢瓦设备留心其导风向按逆主导风向铺设,反搭设长度为150MM,接槎顺直,无孔洞表象,坚固件要可靠,按图纸恳求竖向一般不留搭接缝。
5. The color steel tile equipment should pay attention to its wind direction laid according to the direction of the reverse dominant wind. The length of the reverse erection is 150 MM. The joint is straight and without the appearance of holes. The firmware should be reliable, and the overlap seam should not be left vertically according to the drawings.
6、设备墙板时,用一块3MM的木片放在泛水上,待样板固定后再抽去,这么可以使墙板设备美丽。每5块板都及时用垂线和经纬仪进行一次测量,以防墙板出现倾斜和下口发生变形。
6. When equipment wallboard, put a 3MM piece of wood on the flooding water, and then take it out after the template is fixed, so that the wallboard equipment can be beautiful. Every five panels are measured in time with a vertical line and theodolite to prevent tilting and deformation of the wall panels.